Milestones
5.15.17
- Groundbreaking event for new patient tower on Akron Campus
6.6.17
- New tower foundation started and tower crane installed
10.13.17
- Framing of second level (labor and delivery)
2.12.18
- Concrete pour of fourth floor complete, framing begins for fifth floor (first inpatient unit)
4.24.18
- Employee topping out celebration
5.29.18
- Tower crane removed, windows on the lower levels installed
8.27.18
- Pedestrian bridge to Adolph parking deck and surgery expansion over loading dock in progress
10.22.18
- Windows 95% complete on south face
12.26.18
- West face fully enclosed, pedestrian bridge shell at 90%, surgery expansion at 90%
1.28.19
- Dri Design metal paneling 50% complete pedestrian bridge roof in progress. Surgery expansion roof in progress.
- Dri Design metal paneling 85% completed on upper floors.
2.25.19
- 305 different items for the new tower have been delivered to the Summa Warehouse in preparation for the tower's opening in May.
3.25.19
- Wireless installation complete from basement through fourth floor.
4.1.19
- 365 items, including nine brand new “crash carts,” are now in the Summa Health Warehouse in preparation for delivery to the new tower soon.